[Summit] RIDOT weekly news: Highway Exit Re-Numbering; 6/10 Connector, etc. [weekend mailing no. 1]
David Kolsky
davidjkolsky at yahoo.com
Sat Jan 25 20:28:43 UTC 2020
----- Forwarded Message ----- From: RIDOT Communications <heidi.gudmundson at dot.ri.gov>To:Sent: Friday, January 24, 2020, 02:30:25 PM ESTSubject: We’re resuming our Federally mandated highway mile-marker numbering program next week
| |
|
|
|
|
|
|
| |
|
|
|
| |
|
|
|
|
| |
|
|
|
| STAY CONNECTED
RIDOT's Homepage
Weekly Travel Advisories
Customer Service |
|
|
| |
|
|
| |
|
| Good afternoon, |
| Next week, we’re resuming our Federally mandated highway mile-marker numbering program, starting with I-195, from the I-95 interchange in Providence to the Massachusetts line.
Due to the inclement weather anticipated for this weekend, our work should start on Tuesday night, January 28.
Read more here.
|
|
|
| | |
|
|
|
| |
RIGOV
Official Website for the State of Rhode Island
|
|
|
|
|
|
| _ |
|
|
|
| |
|
|
|
| |
|
| Baker Pines Bridge, Richmond |
| |
| Work Expected: Retaining wall work and steel reinforcement installation in advance of the next concrete pour, Monday-Friday from 7 a.m. to 3:30 p.m.
Traffic Changes: Shoulder closures remain on Route 3 under the bridge for use by construction vehicles and equipment. |
|
| |
|
|
|
| _ |
|
|
|
| |
|
|
|
| |
|
| Carolina Bridges, Charlestown/Richmond |
| |
| Work Expected: Installing rebar, Monday-Friday from 6:30 a.m. to 4 p.m.
Traffic Changes: An alternating one-way traffic pattern, controlled by a temporary traffic signal, is in place on Route 112, from Butter Lane to Carolina Mill Lane. |
|
| |
|
|
|
| _ |
|
|
|
| |
|
|
|
| |
|
| Centerville Road and Toll Gate Road Bridges, Warwick |
| Work Expected: Continuing to build the supports that will eventually help slide the new Centerville Road Bridge into place, Monday-Friday from 7 a.m. to 3:30 p.m.
Traffic Changes: No lane closures anticipated as crews work behind barrier within the staging area on Centerville Road, between the on- and off-ramps for I-95. |
|
| |
|
|
|
| _ |
|
|
|
| |
|
|
|
| |
|
| Kingston Road Bridge, Richmond |
| |
| Work Expected: Utility, highway lighting and drainage work, Monday-Friday from 7 a.m. to 3:30 p.m.
Traffic Changes: Lane shifts on Route 138 remain as does ramp narrowing at Exit 3 off I-95. |
|
| |
|
|
|
| _ |
|
|
|
| |
|
|
|
| |
|
| Route 6/10 Interchange Reconstruction, Providence |
| |
| Work Expected: Installing steel beams for the new Route 6 Viaduct, building the Hartford Avenue and Plainfield Street bridges, and doing utility work on Westminster Street, Monday-Friday from 7 a.m. to 2 p.m.
Traffic Changes: Left lane closure on Route 10 South, from Tobey Street to Union Avenue, Monday-Friday from 7 a.m. to 2 p.m. |
|
| |
|
|
|
|
| |
|
|
|
|
|
|
| |
|
|
|
|
|
| |
|
|
|
| |
|
| January 24, 2020
|
|
|
|
| |
|
|
|
| Department of Transportation, Two Capitol Hill, Providence, RI 02903 | www.ridot.net |
|
|
|
| |
|
|
|
|
|
|
|
| |
|
|
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://sna.providence.ri.us/pipermail/summit_sna.providence.ri.us/attachments/20200125/2326e69f/attachment.htm>
More information about the Summit
mailing list