[Summit] RIDOT Construction updates on the Henderson Bridge and the 6/10 Connector

David Kolsky davidjkolsky at yahoo.com
Sat Jan 9 07:05:40 UTC 2021


 

   ----- Forwarded Message ----- From: RIDOT Business Outreach <sam.guglielmi at dot.ri.gov>To: 
Sent: Friday, January 8, 2021, 1:01:43 PM ESTSubject: Henderson Bridge Update
  
|  |
| 
| 
| 
| 
| 
| 
|   |

 |


| 
| 
|  |

 |

 |


| 
| 
|  |

 |

 |


| 
| _ |

 | 
| 
| 
|  |

 |

 |


| 
|  |

 |


| Henderson Bridge, East Providence/Providence |


|   |


| We have been removing the concrete median barrier and installing a temporary one. This will help delineate the existing Henderson Bridge from the new bridge structure being built. We’ve also been working on the temporary ramp to allow westbound traffic to access South Angell Street and continuing our ongoing activities on Massasoit Avenue, including removal of the existing traffic islands and construction of the new sidewalks and wheelchair ramps.  Work planned for next week includes striping, completion of the temporary ramp at South Angell Street and completion of the project wide temporary traffic signal systems that will help to accommodate the upcoming traffic pattern change, currently scheduled for January 22. More information about this change will be shared with this group, or you can check our News page for our travel advisory once it is posted.
Specific information about the project can be found here. Click here for the latest lane closure information.

|  |  | 
State of Rhode Island: Rhode Island Dep...
 |




| 
| 
|  |

 |

 |


| 
| _ |

 | 
| 
| 
|  |

 |

 |


| 
|  |

 |


| Route 6/10 Interchange Reconstruction, Providence |


|   |


| Starting Sunday night, we are scheduled to remove remnants of the Broadway Bridge and demolish the Westminster Street Bridge over Route 10 North. This will involve a detour of Route 6 East to Union Avenue and back to Route 10 North after 10 p.m. nightly through Friday morning. 
Other scheduled overnight work includes the installation of deck forms and overhang brackets at the Route 10 North to Route 6 West flyover bridge and the construction of retaining walls at the Tobey Street and Harris Avenue bridges. Click here for the latest lane closure information. Read more about the project here. |


| 
|  |

 |

 |



 |


| 
|  |

 |

 |


| 
| 
|  |

 |

 |


|


| 
| 
| 
|  |

 |

 |

 |


| 
| 
|  |

 |

 |


| 
|   |

 | 
| January 8, 2021
For Additional Information:RIDOT Business OutreachSam Guglielmi 401-256-1799 Sam.Guglielmi at dot.ri.gov |

 |


| 
| 
|  |

 |

 |


| 
| Department of Transportation, Two Capitol Hill, Providence, RI 02903 | www.ridot.net |

 |


| 
| 
|  |

 |

 |


| 
|  ‌ ‌ ‌ |

 |


|

 |

 |

 |

 |

 |
|  |


|   
|  
|  RIDOT | Two Capitol Hill, Providence, RI 02903  |
|  
| 
 |
| 
 |
| 
 |

  |
|   
 |

  |

   |

  
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://sna.providence.ri.us/pipermail/summit_sna.providence.ri.us/attachments/20210109/19206f70/attachment.htm>


More information about the Summit mailing list